Tag: home-improvement
-
2024

To our home’s successor, We are finally catching up to current events… in 2024, with very little liquid assets to do any projects, we did what we could. We had quite an opening left on the enclosed wall in the parlor where the sliding door had been and we did not have great working heat…
-
Ending our worst year -2023
We got a quote for painting the house and barn with the understanding that our contractor was still working and would complete painting on his work once completed. We were told the painting crew would start on June 23rd and they’d be done end of July. That did not happen… 2 guys showed up June…
-
2023 porch part 3

In April 2023, decking layout began. M and I helped with this install in May when we took a staycation. It was incredibly fun to help on this and know that we played a small part in our big project. We did a hidden fastener installation with a Camo Marksman. After the crew did some…
-
2023 porch continues

To our home’s successor’s, The guys finished framing the deck late January and started to work on the ceiling. This became our first add. We opted for ceiling coffers which did increase the complexity as well as material cost increase. (this was not our last add… we were easily swayed and it ended up biting…
-
The Porch begins

To our home’s successors, In September 2022, after more than a year of waiting, our contractor team started on demolition and discovery. The porch project as a whole expanded into several projects and a much longer timespan that anyone expected. Our team started by removing the ceilings, they were meticulous and slow as to be…
-
2022 self- performed

To our home’s successors, With our major project on deck for the year, we tried our best to stay motivated and accomplish a few projects on our own as well. We started on some low hanging projects that were mostly aesthetic. We had shifted primary rooms in 2021 which gave us ‘his and hers’ closets…
-
2021

With 2020 spent primarily in global lockdown, many factories were then behind on production and often short staffed when they were finally able to reopen. The limited supply meant high costs for materials… just in time for us to do a major project… With this as our outlook, we decided to take it as easy…
-
Downstairs bathroom

To our home’s successor, We spent the first couple years exclusively using the downstairs bathroom as it was in a better state than the upstairs bathroom despite it’s inconvenience. After showering several times, we started to notice the state of the walls. There was (and at this time, still isn’t a ventilation system in either…